You can create a new schedule policy to perform auxiliary copy operation.
Before You Begin
You must have appropriate permissions to create a schedule policy. For more information, see User Security Permissions and Permitted Actions by Feature: Schedule Policy.
Procedure
-
From the navigation pane, go to Manage > Schedules.
The Schedules page appears.
-
Select Schedule policies tab.
The Schedule policies listing page appears.
-
At the top-right of the page, click Add.
The Select Schedule Policy Type page appears.
-
Select Auxiliary Copy, and then click Next.
The Add Schedule Policy page appears.
-
Enter the following information in different tabs:
-
General Settings
- In the Name field, enter a descriptive name for the schedule policy.
-
Configure Backup Options
-
Under Tape Media Options, configure the following:
. Start new media: Enable this option to start backups on a new tape media.
. Mark media full on success: Enable this option to mark the media as full after a successful backup.
-
-
Define Pattern
By default, the Client time zone is selected to run scheduled tasks using the local time zone of the client.
-
Select the desired pattern for the schedule (for example, Daily, Weekly, or Monthly).
-
Configure additional recurrence options, such as start time, repeat frequency, and end date, to control when and how often the schedule runs.
-
-
Configure Common Options
-
Adjust advanced settings for the schedule policy, if available.
-
Options may include retry intervals, job priorities, or notifications based on your environment.
-
-
Set Associations
-
From the Associations page, select the storage policies or storage policy copies that you want the schedule policy to apply to.
-
Review your selections to confirm they match your intended scope.
-
-
-
Click Save.
-
Click Submit.