Re-Copy a Job associated with a Copy

Updated

You can re-copy fully or partially copied jobs associated with a storage policy copy. When the partially copied job is re-copied, all the data chunks in the selected job from the beginning of the job is copied.

Notes

  • Data can only be re-copied if it still exists in the source copy.

  • You cannot re-copy a backup copied job or a replicated job from the snapshot copy.

Applies To

Synchronous Copy, Selective Copy, Spool Copy, Parallel Copy, Inline Copy, Deferred Copy, and WORM Copy

Procedure

  1. From the CommCell Browser, expand Policies > Storage Policies > storage_policy.

  2. Right-click the appropriate storage policy copy, click View> Jobs.

  3. In the Job Filter for Storage Policy dialog box, clear the Specify Time Range check box, and then click OK.

    A list of jobs associated with the copy are displayed in the right pane of the CommCell Browser.

  4. Right-click the appropriate available job, then click Re-Copy.

    To select multiple jobs, hold down the Ctrl key and right click on the jobs.

    A message appears that asks if you want to re-copy the selected job.

  5. Click Yes to continue.