You can configure the time of day that you want to initiate scheduled jobs for a replication group. The time zone of the replication group is used for the job start time.
If the job start time that you set is not within the time period that is set in the Replication window, then the software considers the next available time within the window as the start time.
Procedure
From the navigation pane, go to Disaster recovery > Replication.
The Replication groups page appears.
Under Group name, click a replication group.
On the Configuration tab, in the RPO area, by Job start time, click
Edit.
In the time dialog box, enter a time, and then click
Save.